ADEAM Unit Cap Construction Method construction example 1

Site place:
Kochi

Greening wall that harmonizes with nature

Because there was concern about short bearing capacity, a large project with a wall area of ​​1300 m² was adopted by proposing a reinforced embankment (1:0.6 gradient). This embankment contributes to bring many peoples to come and see the 500-year-old cherry blossom.
Kochi Prefecture Sakura Line construction work,

• Wall height (m): 12.4

• Wall gradient : 1.0.6 

• Approximate wall area (m²): 1300

Products: Geotextile “ADEAM” for embankment and ground reinforcement

Previous page

Related products / construction methods